Getting Started: Initial Information and Consultations
A staircase installation is typically carried out in two phases: the installation of the stair skeleton and the installation of finishing materials.
To secure the skeleton to the house structure, flanges, brackets, and bolts may be used. For a minimalistic look, all connecting hardware should be concealed. To achieve this, the stair skeleton should be installed before other finishing materials, particularly in areas where the skeleton touches floors or walls. The hardware should be sunk behind the structure to allow finishing materials, like flooring, to run over it seamlessly.
The stair skeleton can also serve as a construction staircase. Stair finishing materials, such as wood and glass, should be installed as late as possible, typically at the end of the construction process.
1-3 DAYS
1-3 DAYS
additional notes for builder:
additional notes for builder:
1-3 WEEKS
1-3 WEEKS
additional notes for builder:
additional notes for builder:
4-7 WEEKS
4-7 WEEKS
additional notes for builder:
additional notes for builder:
1-3 DAYS
1-3 DAYS
additional notes for builder:
additional notes for builder:
additional notes for the builder
additional notes for the builder
1-2 WEEKS
1-2 WEEKS
4-6 WEEKS
4-6 WEEKS
additional notes for the builder
additional notes for the builder
1-2 WEEKS
1-2 WEEKS
! NOTE: This timeline provides a general guideline.
© mrail